The government is considering the allocation of additional berths at the Tema Port to speed up the clearance of clinker and reduce demurrage costs incurred by cement manufacturers.
Transport Minister Joseph Bukari Nikpe said he and Trade, Agribusiness and Industry Minister Elizabeth Ofosu-Adjare are expected to visit the port to identify areas that can be made available for vessels carrying the key cement raw material.
The move comes amid growing congestion at the Tema Port, where limited berthing space and rising cargo volumes have contributed to delays in the clearance of clinker.
The delays have resulted in demurrage charges for cement manufacturers, with the additional costs cited among factors behind the recent GH¢12 increase in the price of a bag of cement.
Speaking on The Point of View on Channel One TV, Mr Nikpe said cement manufacturers currently have access to two berths but are seeking additional space to allow their consignments to be processed more quickly.
“The Cement Manufacturers, their problem is that we have allocated two berths for them. They want more berths so that their clinker comes, they will be cleared quickly. As I mentioned, the containerized cargo has also increased.
“There’s competition for space at the port to be able to serve all our importers. Friday, myself and the Minister for Trade, Honourable Elizabeth will be going to the port to see how we can also see which of the areas we can cede off to support the clearance of the cement raw materials that they are importing so that at least they will not be faced with any damage or any other extra charges,” he noted.
Mr Nikpe said the government’s intervention is intended to reduce the additional costs associated with delays at the port and improve the movement of cargo.
Beyond the issue of berthing space, the government is also seeking to increase the port’s equipment capacity, with the Ghana Ports and Harbours Authority (GPHA) directed to acquire two additional cranes.
According to the Transport Minister, the equipment will help accelerate the loading and unloading of vessels and prevent shipping lines from incurring unnecessary demurrage.
“I also instructed the Ghana Ports and Harbours Authority for them to acquire two cranes that will be able to load and offload quickly so that all the ships or all the shipping lines coming in with cargo would not have any issue in terms of delay that would have caused them to pay demurrage any longer.
“So they are going to do an emergency acquisition of two cranes that will augment already what they have on the ground that will facilitate the loading and offloading of cargo, and it is believed that we will be able to decongest the port,” he noted.
The proposed additional berths and emergency acquisition of cranes form part of measures being pursued by government to ease pressure on the Tema Port and minimise delays affecting importers.