The Tema Oil Refinery (TOR) has officially resumed crude Tema Oil Refinery (TOR) refining operations after several years of inactivity, marking a major milestone in Ghana’s downstream petroleum sector and efforts to stabilise domestic fuel supply.
The resumption follows the successful completion of extensive Turnaround Maintenance (TAM) works on the refinery’s Crude Distillation Unit (CDU), undertaken between 1 August and 30 October 2025. The maintenance programme, according to TOR, was executed within three months and in strict adherence to international engineering, safety and operational standards .
After the maintenance works, the National Petroleum Authority (NPA) conducted comprehensive regulatory inspections to assess the refinery’s readiness. TOR subsequently received full regulatory clearance, having met all mandatory safety and operational requirements, paving the way for refining activities to restart.
Refining operations officially began on Friday, 19 December 2025, with all lines of petroleum products being routed into storage — the first time in several years that the refinery has processed crude oil at this scale.
TOR says the refinery will operate under a phased transition model in the coming months, ahead of its official recommissioning. This approach is intended to stabilise operating systems, optimise performance and ensure long-term operational reliability.
Currently operating at about 28,000 barrels per stream day (bpsd), the refinery is expected to scale up significantly following the installation of a new furnace, identified as F-61. The furnace has already been installed and is awaiting commissioning and integration into the CDU.
Once fully operational, the F-61 furnace will enable TOR to restore its original nameplate capacity of 45,000 bpsd. Management has also outlined a strategic pathway to expand refining capacity further to 60,000 bpsd in the medium term, subject to the installation of a new air-cooler system .
The Government of Ghana is expected to formally commission and tie in the new furnace at a later date, with details of the event to be communicated to stakeholders and the general public in due course.
TOR’s management expressed appreciation to President John Dramani Mahama for what it described as his continued support, vision and commitment to restoring the refinery as a critical pillar of Ghana’s energy infrastructure.
The refinery also acknowledged the role of the Minister for Energy and Green Transition, Dr John Abdulai Jinapor, citing his policy leadership, technical oversight and hands-on engagement as instrumental in bringing the refinery back to operational life.
According to TOR, the revival aligns with broader national energy priorities, including reducing fuel imports, strengthening energy security and improving the efficiency of Ghana’s downstream petroleum value chain.
Management further commended the Board of Directors, staff and management of TOR for their resilience and professionalism throughout the revival process, noting that employees remain committed to sustaining the refinery’s renewed momentum and achieving operational excellence.
The Board and Management also thanked the Government, industry stakeholders and the Ghanaian public for their confidence and support during what it described as a challenging but transformative period for the refinery.
The resumption of operations at TOR is expected to play a key role in Ghana’s energy sector, particularly as the country seeks to improve local refining capacity, manage fuel supply disruptions and stabilise prices in the medium to long term.