The Ghana Arbitration Centre (GAC) has, in a unanimous decision, ordered Justmoh Construction Limited to refund US$33.3 million to Ashanti Port Services Limited (APSL) as the outstanding balance of advance mobilisation payments arising from disputes over the Boankra Inland Port (BILT) project.
The tribunal further ruled that the amount shall attract simple interest at four per cent per annum, calculated from 30 days after receipt of the award until full payment.
However, the tribunal also directed Ashanti Port Services Limited to pay Justmoh Construction Limited US$7,107,456.70 in compensation for earthworks executed at the project site.
On costs, Justmoh Construction Limited was ordered to bear 75 per cent of Ashanti Port Services’ legal fees, as well as 75 per cent of the Claimant’s share of the arbitrators’ and administrative fees. The costs awarded amount to US$226,875 and GH¢26,250, with no interest accruing on the sum.
The arbitration proceedings involved Ashanti Port Services Limited as the Claimant and Justmoh Construction Limited as the Respondent. The Claimant was represented by G.A. Sarpong & Co., while the Respondent was represented by Owusu-Ankomah, Arvoh Mensah, Dzigba & Associates.
The dispute formally commenced on 19 December 2023, when the Ghana Arbitration Centre received Ashanti Port Services Limited’s Notice of Arbitration. This was followed by the Respondent’s response on 10 January 2024 and the Claimant’s reply on 22 January 2024.
On 12 February 2024, the GAC constituted a three-member arbitral tribunal comprising Emmanuel Amofa, Professor Richard Frimpong Oppong, and Justice Nene A.O. Amegatcher, who served as Chair. Neither party raised any objection to the composition of the tribunal.
A virtual arbitration management conference held on 5 March 2024 resulted in the parties agreeing that certain preliminary matters should be determined first. These included the Respondent’s challenge to the tribunal’s jurisdiction and the Claimant’s applications for interim injunction and preservation orders.
Following the exchange of affidavits and written submissions, the tribunal held an online oral hearing on 2 April 2024, at which both parties were represented by counsel and presented arguments on the preliminary issues.
After the post-hearing briefs were filed, the tribunal concluded the hearings on the preliminary matters and issued its Award on Jurisdiction and Interim Relief on 17 May 2024, thereby paving the way for proceedings on the substantive merits of the dispute.
A central issue before the tribunal was whether the earthworks undertaken by Justmoh Construction were worth approximately US$33 million, as claimed by the Respondent. Ashanti Port Services Limited argued that the value of the earthworks did not exceed US$4 million, relying mainly on earlier projections.
The tribunal, however, found that the Claimant failed to provide independent evidence or expert testimony to support its valuation. It noted that Ashanti Port Services Limited did not conduct its own independent assessment of the cost of the earthworks.
Justmoh Construction Limited, for its part, relied on interim payment certificates, monthly progress reports, photographs, designs, and correspondence from the independent consultant, Vision Consult. The Respondent also cited correspondence in which the Claimant acknowledged that the value of works executed exceeded US$33 million.
While noting that earthworks were not expressly stipulated in the Boankra Contract, the tribunal accepted that substantial works had been carried out, supported by documentary and photographic evidence presented during the proceedings.
In its final award, the tribunal held that Justmoh Construction Limited lawfully terminated the Boankra Contract, thereby resolving the dispute concerning the contract’s termination.
All other claims and requests for relief by both parties were dismissed, bringing the arbitration proceedings at the Ghana Arbitration Centre to a close.
Ashanti Port reacts
Reacting to the ruling, Nana Afum Dwamena III, the Kwahu Nkwatia Benkumhene and Chief Executive Officer of Ashanti Port Services Limited, expressed satisfaction with the arbitration outcome.
Speaking in an interview with Despite Media, the traditional ruler said he accepted the tribunal’s decision, describing it as providing clarity and closure to the matter.
According to Nana Afum Dwamena III, the ruling demonstrates the strength of Ghana’s alternative dispute resolution mechanisms and underscores the importance of resolving disputes through lawful and institutional processes.
He noted that arbitration remains a credible means of settling complex disputes, particularly those involving large-scale infrastructure projects and contractual obligations.
While acknowledging that arbitration outcomes may not always fully satisfy all parties, the Kwahu Nkwatia Benkumhene stressed that respect for final decisions is essential to sustaining confidence in the justice system.
He added that prolonged disputes often delay development and create uncertainty, which can negatively affect communities and deter investment.