Ghana’s cement industry is facing potential price increases as delays in the delivery of clinker — a key raw material in cement production — continue to disrupt operations at the nation’s ports.
Prolonged congestion within the harbour has left vessels carrying clinker waiting between 13 and 20 days to berth, with some shipments stranded offshore for up to three weeks. The delays have resulted in mounting demurrage charges, significantly raising operational costs for manufacturers.
An emergency meeting was convened on Monday, 23 February 2026, by the Minister for Trade, Agribusiness and Industry, Elizabeth Ofosu-Adjare, in collaboration with the Minister for Transport, Joseph Bukari Nikpe. The meeting brought together cement manufacturers, port authorities and industry stakeholders to address the operational bottlenecks affecting clinker shipments.
Participants at the meeting noted that vessels are incurring high costs due to extended waiting periods before berthing.
Chief Executive Officer of the Chamber of Cement Manufacturers Ghana (COCMAG), Bishop Dr George Dawson-Ahmoah, described the situation as a financial “leak” impacting manufacturers. He indicated that rising demurrage charges are placing a heavy burden on the industry and warned that the increased operational costs could be passed on to consumers.
Minister Joseph Bukari Nikpe assured stakeholders that efforts are underway to fast-track ongoing dredging works at the port. The dredging project, expected to be completed by the end of June 2026, is aimed at improving the port’s capacity.
Currently, the harbour can accommodate vessels of up to 8,000 tonnes. Upon completion of the dredging works, it is expected to handle vessels carrying up to 20,000 tonnes, a move anticipated to reduce waiting times and ease congestion.
In the interim, industry players have proposed temporary measures, including the allocation of additional berths for clinker shipments and the handling of non-dust producing materials such as gypsum and slag at alternative berths to reduce congestion and speed up discharge processes.
Stakeholders have called for urgent action to stabilise operations and prevent further disruptions within the cement supply chain.