The Ghana Grid Company Limited (GRIDCo) has attributed Thursday morning’s widespread power outage to a major fault on the Akosombo–Volta transmission line, which triggered the automatic shutdown of the Akosombo generating units and some thermal plants.
The incident occurred at about 4:30 a.m. on Thursday, August 20, 2026, resulting in the loss of power supply to parts of the country.
GRIDCo said the shutdown of the generating units was activated automatically by the power system’s protection mechanisms to safeguard the integrity and stability of the National Interconnected Transmission System.
The company said its engineers immediately began working with other power sector agencies to contain the disturbance and restore electricity to affected areas.
“Immediately following the incident, GRIDCo engineers, working in close coordination with other power sector agencies, took steps to isolate the affected transmission line and commenced the safe and systematic restoration of the power system,” the company said in a statement.
According to GRIDCo, power supply has already been restored to some affected areas, while efforts are ongoing to reconnect all remaining customers.
“Power supply has already been restored to some affected areas, and restoration efforts are progressing steadily to ensure that supply is restored to all remaining affected customers as quickly and safely as possible,” it said.
GRIDCo said all relevant technical teams have been fully mobilised and are working with urgency to restore the national power system.
The company expressed regret over the inconvenience caused by the outage and assured the public that restoration efforts would continue until full supply is achieved.
GRIDCo said it would provide further updates as more information becomes available and appealed to the public for patience and cooperation while the technical teams work to complete the restoration.