Parts of the Greater Accra Region will experience a prolonged power outage on Sunday, 16 August, as the Ghana Grid Company (GRIDCo) carries out emergency repairs on a damaged transmission tower at Ashaiman.
The outage, scheduled from 3:30am to 6:00pm, is required to enable engineers to replace the damaged tower on the Tema–Achimota 161kV transmission line.
GRIDCo said the tower was damaged following a fuel tanker explosion that occurred while welding work was being carried out on the tanker within the transmission line’s Right-of-Way.
In a statement issued on Saturday, 15 August, the company said the emergency repairs are necessary to restore the integrity of the transmission line and maintain the reliability of electricity supply.
GRIDCo apologised to affected customers and appealed for their patience as engineers undertake the repair works.
The company also renewed its warning against encroachment on transmission line corridors, stressing that such activities are prohibited under the Transmission Line Protection Regulations, 1967 (L.I. 542), as amended.
It said unauthorised construction, excavation, commercial activities, garages, shops, lorry parks and other developments within transmission corridors pose serious safety risks and can disrupt the operation of the national transmission network.
GRIDCo further disclosed that, following a directive from the Minister for Energy and Green Transition, John Abdulai Jinapor, individuals, businesses and land users unlawfully occupying transmission line Rights-of-Way have been given one month to vacate the affected areas.
The company said it will work with Metropolitan, Municipal and District Assemblies, statutory institutions and security agencies to remove unauthorised structures and enforce the regulations after the deadline.
The emergency repairs are expected to restore the affected transmission infrastructure and strengthen the reliability of power supply in the affected areas.