The Minister for Health, Kwabena Mintah Akandoh, has dismissed claims that government is responsible for delays in opening the 120-bed Children’s Specialist Hospital at Weija, attributing the hold-up to outstanding works by the contractor.
Addressing Parliament on Wednesday, 8 July, Mr Akandoh said the Ministry is ready to commence operations at the facility but is awaiting the formal handover of the project after the completion of some critical works.
He explained that some aspects of the project, including the installation of certain medical equipment, remain unfinished, preventing the Ministry from taking full control of the facility.
According to the Minister, the World Bank-funded project encountered procurement challenges during construction, which affected its progress.
“Mr Speaker, I inherited the project. It’s a World Bank-funded project, and in the course of the construction, the World Bank raised issues of what we call misprocurement, and so we had to deal with the issues of misprocurement,” he told Parliament.
Mr Akandoh said the Ministry has engaged the contractor on several occasions to resolve the outstanding matters and is expected to hold a final meeting with the contractor on July 10.
He explained that the contractor, who is currently outside the country, requested to be present in person to help conclude discussions on the remaining issues.
The Minister rejected suggestions that the government was intentionally delaying the commissioning of the facility, noting that assessments by the Ghana Health Service revealed that parts of the project were yet to be completed.
He assured Parliament that the Ministry had already recruited the necessary staff and would be able to begin operations immediately once the facility is handed over.
“If the project is handed over this morning, within the next 24 hours, we don’t even need any fanfare. We will commission the project because we have the full complement of staff for that particular facility,” he said.
The development follows growing public pressure from residents of Weija-Gbawe, who in May demonstrated to demand the immediate opening of the hospital.
The 120-bed Children’s Specialist Hospital, when operational, is expected to improve access to specialised healthcare for children and reduce pressure on existing health facilities.