The Minister for Energy, John Jinapor, has announced the full restoration of power generation at the Akosombo Dam following recent disruptions caused by a fire outbreak.
In a Facebook post on Friday (1 May), the Minister stated that all generation units are back in operation and supplying power to the national grid.
“Mission accomplished. All generation units are now back in service,” he said, indicating a return to normalcy after days of intermittent power outages.
Mr Jinapor explained that the restoration was achieved through coordinated efforts by engineers, technicians and emergency response teams who worked continuously to stabilise the system.
He also commended key power sector institutions, including the Ghana Grid Company, Volta River Authority and the Electricity Company of Ghana, for their collaboration in resolving the situation.
The disruption followed a fire outbreak at a substation operated by the Ghana Grid Company at Akosombo, which resulted in the loss of more than 1,000 megawatts of power and triggered outages in parts of the country.
With all units now operational, authorities say the power system has regained stability, restoring supply to affected areas.