Passenger services on the 97.7-kilometre Tema–Mpakadan railway will officially begin on 1 October 2025, Transport Minister Joseph Bukari-Nikpe has announced. The confirmation marks a key milestone for Ghana’s rail revival programme after years of construction setbacks and technical tests.
Speaking at the Government Accountability Series press briefing in Accra on Wednesday, 17 September, Mr Bukari-Nikpe said the project has cleared all operational checks.
“We have done a test run on the Tema–Mpakadan rail line, and it ended yesterday. So, by October 1, God willing, we will start the first operations from Tema to Mpakadan. We have finished with the test runs and everything is set for us to start operations,” he said.
The Tema–Mpakadan stretch forms the opening phase of the ambitious Eastern Corridor Railway, which is designed to link Ghana’s principal port at Tema to the country’s northern frontier and eventually extend into Burkina Faso, strengthening regional trade routes.

Constructed by Afcons Infrastructure of India and financed through a US$447 million credit facility from India’s Export–Import Bank, the project was inaugurated in November 2024. Engineers completed a series of comprehensive trial runs over several months, including final tests that wrapped up on 16 September 2025, clearing the way for passenger operations.
Initial forecasts suggested commercial service might not begin until mid-2026 following a test-train accident in April 2024 and repeated incidents of vandalism that damaged track components and signalling equipment. In May 2025, the Ghana Railway Development Authority reported that about 75 percent of repair work had been completed, but an official start date remained uncertain until Wednesday’s announcement.
Mr Bukari-Nikpe revealed that two passenger coaches have been prepared for the launch, with schedules designed to ease congestion on the heavily trafficked Tema–Afienya corridor.
The railway is expected to speed up the movement of goods from the port to inland markets and create jobs in operations, maintenance and related services. There are also plans to extend the network beyond Mpakadan toward the Volta Region and northern Ghana as part of a broader rail development strategy.
Two passenger coaches have been prepared for the launch, which is anticipated to reduce road congestion along the busy Tema–Afienya corridor and provide commuters and businesses with a reliable alternative mode of transport.