Source: The Ghanaian Times
The Ofankor-Nsawam road expansion project on the Accra-Kumasi Highway is facing another delay after the contractor, Messrs Meripoma Enterprise Limited, requested a further extension of time to complete the works.
The 33.4-kilometre project, which began in July 2022 and was originally scheduled for completion in July 2024, has already missed its initial deadline, raising renewed concerns among commuters and motorists.
With only months left to the revised completion timeline, the contractor has indicated that it will not be able to finish the project as scheduled, prompting fresh frustration from road users who continue to endure heavy congestion, dusty conditions, and damaged vehicles along the stretch.
A visit by The Ghanaian Times to sections of the road, including Amasaman, Sapeiman, Sasam, Hebron, Medie, and Dobro, revealed deep potholes, muddy surfaces, and long traffic queues, particularly during peak hours.
Some commercial drivers say the poor state of the road has worsened due to the rains, increasing travel time and vehicle maintenance costs.
Kwame Opoku, a driver who uses the stretch regularly, said the road had become “almost unbearable,” adding that his daily earnings had been affected due to longer travel times.
Another driver, Yaw Mensah, questioned whether the project could realistically be completed within the revised timeframe, citing the slow pace of work and limited workforce on site.
He also raised concerns about a police barrier at Dobro, alleging that it contributes to traffic congestion along the corridor. He called for a review of the arrangement to ease movement of vehicles.
Commuters and traders have also expressed concerns over the impact of the road condition on transport fares, business activities, and general mobility.
Madam Efua Owusu, a trader who frequently travels between Accra and Amasaman, said transport costs had increased, while breakdowns and delays had become more frequent.
Isaac Tetteh, another commuter, urged authorities to compel the contractor to accelerate work, warning that conditions could worsen further if the rains persist.
Officials supervising the project have disclosed that the road is currently about 82 per cent complete.
The Chief Resident Engineer of Associated Consultants, Kwabena Bempong, confirmed that the contractor had formally requested an extension of time, adding that completion by July was no longer feasible given the current pace of work.
He said discussions were ongoing regarding the duration of the extension, noting that compensation challenges had contributed to delays on the project.
The Resident Engineer (Roads), Thomas David Arthur, said measures were being taken to reduce inconvenience to motorists, including routine maintenance works such as pothole patching, grading, and compaction on unpaved sections.
He added that the contractor had been directed to promptly repair potholes caused by rainfall to improve traffic flow.
According to him, the Pobiman flyover is expected to be opened to traffic by the end of June 2026, while the Medie flyover is scheduled for completion by the end of July 2026.
He further disclosed that preparatory works for the Nsawam bypass interchange would commence once outstanding compensation issues are resolved.
The Ofankor-Nsawam project forms part of the National Road Six (N6) corridor and includes interchanges, flyovers, bridges, and footbridges at key locations such as Amasaman, Pobiman, Medie, and Nsawam Junction.
When completed, the project is expected to ease congestion along the Accra–Kumasi highway and improve transportation and economic activity along the corridor.