Electricity supply in Kumasi and the wider Ashanti Region is set for a major boost as work enters the final phase of the Kumasi–Anwomaso Transmission Line Upgrade (K1–K2 Project), Energy and Green Transition Minister Dr John Abdulai Jinapor has announced.
During an inspection of the project at Anwomaso in the Ashanti Region, the Minister said the upgrade will replace the existing 19-kilometre single-circuit 364MVA transmission line with a double-circuit 978MVA transmission line, more than doubling the network’s current transmission capacity.
The project also includes the upgrade of a transformer at the Kumasi (Ahodwo) Substation, where capacity will increase from 66MVA to 145MVA, a move expected to improve the reliability, stability and resilience of electricity supply across the region.
Construction is scheduled to enter its final phase from Monday, July 20, 2026, during which some customers may experience temporary and localised power outages to allow the works to be completed safely.
Dr Jinapor said the short-term interruptions are necessary to deliver a more robust electricity transmission system capable of supporting the growing energy demand of Kumasi and surrounding communities.
He appealed to residents and businesses to cooperate during the period, assuring them that the Ghana Grid Company (GRIDCo) and the Electricity Company of Ghana (ECG) would work to minimise disruptions and restore power as quickly as possible.
The Minister expressed appreciation to residents for their patience and support, describing the project as a critical investment in strengthening power infrastructure and supporting economic growth in the Ashanti Region.