Finance Minister Dr. Cassiel Ato Forson has highlighted progress in Ghana’s Gas-to-Power Strategy, aimed at shifting electricity generation from costly light crude oil to locally produced natural gas.
Presenting the 2026 Budget Statement, themed “The Ghana We Want,” to Parliament on Thursday, 13 November 2025, Dr. Forson said the transition is expected to lower generation costs by at least 75 percent, reduce financing gaps in the energy sector, and strengthen fiscal sustainability.
“This transition will significantly cut generation costs, reduce the energy sector’s financing shortfalls, and enhance energy security, while supporting Ghana’s climate commitments,” he said.
The Minister revealed that partners in the Offshore Cape Three Points (OCTP) project, led by ENI, completed a major upgrade in July 2025, raising gas processing capacity from 240 million to 270 million standard cubic feet per day.
He added that gas production from the Jubilee and TEN fields has increased from 110 million to around 130 million standard cubic feet per day, with agreements now in place to further boost supply.
“We have secured an additional 80 million standard cubic feet per day from OCTP partners led by ENI,” Dr. Forson stated. He also confirmed an agreement with Jubilee partners to raise production by 70 million standard cubic feet per day, which will require expanding processing facilities.
To manage the expansion, the government has set up a project implementation committee to oversee the accelerated construction of Ghana Gas Processing Plant Two (GPP 2), which will handle the increased gas output for electricity generation.
The initiative is part of a broader strategy to improve energy security, cut power generation costs, and support Ghana’s transition to cleaner and more sustainable energy sources.