The westbound carriageway of the Dr Busia Highway from Pamprom Junction will be closed from September 7, 2026, to allow major drainage works under the Greater Accra Resilient and Integrated Development (GARID) Project.
The first phase of the closure will run until the end of November, with Pamprom Junction expected to reopen in the first week of December.
The works involve the construction of a 1.5-kilometre double-cell underground rectangular stormwater drain from Pamprom Junction to First Light Junction in the Kaneshie area.
The new drain will be about 10 metres wide and replace the existing twin 1.2-metre-diameter pipe system serving the area.
It will also connect the recently completed drainage section at Accra Academy to the existing drain at Pamprom Junction.
Coordinator of the GARID Project and member of the Post-Flood Mitigation Committee, Kojo Ohene Safo, announced the traffic restrictions during the Accountability Series on Wednesday, August 26.
He said the scale of the construction made temporary road closures necessary, adding that GARID had developed a traffic management plan with the Department of Urban Roads to reduce disruption to motorists.
The first phase will affect motorists travelling from Korle Bu, Graphic Road, Obetsebi Lamptey Circle, Kwame Nkrumah Circle and adjoining routes towards First Light Junction.
Affected motorists will be diverted through Awudome Cemetery Road, New Times Road, Awudome Roundabout, Oblogo and Mataheko before reconnecting at First Light Junction.
Motorists may also use the Obetsebi Interchange–Oblogo Traffic Light–Mataheko corridor.
GARID said directional and advance warning signs would be installed along the affected routes to guide motorists.
The Motor Traffic and Transport Department and relevant assemblies will also support traffic management during the closure.
Although Pamprom Junction is expected to reopen in December 2026, the westbound section between Kaneshie Station and First Light Junction will remain closed until August 2027 as construction continues.
The third phase is scheduled to begin in September 2027 when the works reach First Light Junction.
That phase will involve the temporary closure of the road linking First Light Junction to the Cocoa Clinic Roundabout until the end of October 2027.
GARID has urged residents, commuters, transport operators and businesses to plan their movements ahead of the closures and avoid the construction areas where possible.
Road users have also been encouraged to use the designated diversion routes unless they have legitimate business within the affected areas.